Duplex 6'x10' Lift Station Near
Road • 119gpm
SITE DETAILS
Existing lift station was aging and needed to be replaced. Due
to site topography, areas sewer terminated approximately 8'
below the nearest gravity sewer, thus requiring a lift station.
Romtec Utilities was the solution.
Replacement for an aging existing lift station located
adjacent a main roadway; 119 GPM @ 32' TDH (duty point)
THIS ROMTEC UTILITIES SYSTEM
INCLUDED
City specified:
MultiTrode MT2PC controller, MultiTrode PumpView SCADA
system
Concrete wet well:
fall & confined space entry control, pedestrian rated
hatch
Pump disconnect
panel: with free air stand, cable hatch
Piping &
accessories: all stainless steel
ITT Flygt pumps:
NP3085 MT, 3 HP
Level monitoring &
control: Primary - MultiTrode probe, Redundant / Back-up
- MultiTrode probe w/MTR relays
Concrete valve vault:
Pedestrian rated hatch, 4" system, check & plug valves,
discharge pressure gauge, by-pass pumping port
Electrical controls:
UL listed
Communication:
telephone alarming, cellular web-based SCADA system