Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station

Marine Corps Base Camp Pendleton Marine Corps Base Camp Pendleton
Installation of the Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station Installation of the Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station
Construction of the Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station Construction of the Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station
Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station Marine Corps Base Camp Pendleton – Large Wet-Dry Lift Station

Project Assets

Project Description

The Marine Corps Base Camp Pendleton needed this large wet-dry wastewater lift station to replace an existing system to allow the construction of new enlisted quarters. The new lift station included triplex dry-pit pumps to handle super-high flows of sewage from the facilities. An 8’ diameter precast concrete sump collects the sewage. Suction lines connect the sump to a 200-square-foot rectangular dry pit where the pumps, flow meter, and valve assembly are located. This lift station also includes an upstream grinder pit with a Macho Monster sewage grinder to pulverize solids into passable sizes.

What Romtec Utilities Provided

  • Lift Station Design & Engineering
  • Package Lift Station Supplier
  • Package Lift Station Manufacturer
  • Lift Station Site Plan Layout Designer
  • On-Site Lift Station Construction Adviser
  • On-Site Start-Up Management
1,585 25′
GPM TDH

Why They Chose Romtec Utilities

When Harper Construction won the design-build contract for bachelor’s enlisted quarters at Camp Pendleton, it contacted Romtec Utilities to provide the lift station replacement. Working directly with Harper Construction and the engineering corps at Camp Pendleton, Romtec Utilities proposed a submersible lift station design for the replacement. This design was changed to include a meter vault, a grinder vault, and an odor control system. The added components led Camp Pendleton and Harper Construction to request an alternate design with a wet-dry configuration. Romtec Utilities provided new designs for a sophisticated wet-dry wastewater lift station. The wet-dry configuration was not as economical, but for Camp Pendleton and Harper Construction to advantages for maintenance, ease of use, and sophistication was better aligned to their goals and preferences.

Camp Pendleton, CA|1,585 GPM – 25′ TDH