Duplex 6'x22' Pump Station for
Street Improvement
SITE DETAILS
New street improvement lowered the road grade to pass under a
railroad crossing; this created a low spot that collected all
the storm runoff, thus requiring a lift station. Romtec
Utilities was the solution.
Street improvement
constructing an underpass at a railroad crossing; major
thoroughfare reconstructed to pass under a railroad
track
THIS ROMTEC UTILITIES SYSTEM
INCLUDED
City specified: MT2PC controller,
magnetic flow meter, SCADA system, auxiliary power
Concrete wet well: fall &
confined space entry control
Pump disconnect panel: with free
air stand, cable hatch
Piping & accessories: all
stainless steel
ITT Flygt pumps: NP3127 MT, 10
HP
Level monitoring & control:
Primary -MultiTrode probe, Redundant / back-up - Multitrode
probe w/MTR relays, High water holdout - ITT Flygt
ENM-10
Concrete valve vault: fall &
confined space entry control, 6" system, check & gate
valves, discharge pressure gauge
Concrete meter vault: Seimens
Mag-meter
Generator: Cummins 35 kW w/A.T.S.,
diesel fuel, sound attenuation
Electrical controls: UL
listed
Communication: Dry contacts, Owner