What does the start-up technician check before starting the pump station for the first time?

jweddell

The Romtec Utilities start-up technician follows a Field Start-Up Report that is configured to each specific system. Our technician will typically run through these assessments before starting-up the lift station: Structural/Mechanical Construction, Electrical Construction and Connections, Water Availability, Pump and Pump Control Data, Communication Equipment, Physical Inspections, Back-Up Power Generator (if applicable), Pre-Start-Up Pump Electrical Checks, Operational Checks, Draw Down Test, Pressure Readings, Primary and Secondary Level Sensing.