Microsoft Columbia Data Center – Identical Wastewater Lift Stations
Project Description
Four identical lift stations were supplied to address sewage and cooling process wastewater from this commercial facility. This was the final of four lift stations supplied to Microsoft’s 70-acre data center. Aircraft rated hatches are included for each lift station to handle heavy forklift traffic. Ebara submersible sewer pumps handle the medium flow and average head condition of the system. An outdoor UL listed control panel utilizes an intrinsically safe barrier for in-well electrical controls and utilizes float controls for liquid level-sensing.
What Romtec Utilities Provided
- Lift Station Design & Engineering
- Package Lift Station Supplier
- Package Lift Station Manufacturer
- On-Site Lift Station Construction Adviser
- On-Site Start-Up Management
120 | 70′ |
GPM | TDH |
Why They Chose Romtec Utilities
The design and construction of this 500,000-square-foot data center was handled by M+W Group (Civil E.) and McKinstry Group (GC). Romtec Utilities was specified by M+W Group to provide the design, engineering, and supply services for four site specific package lift stations. For a project this size, choosing Romtec Utilities to perform these services provided more time for M+W Group and McKinstry Company to focus on areas more closely aligned in their areas of expertise. Romtec Utilities was able to meet their requirements and expectations while remaining within the budget of Microsoft.