Kings Mountain Energy Center

Middletown Energy Center|Middletown, OH|480-850 GPM - 25'-35' TDH

jweddell300gpm - 500gpm, 500gpm - 1,000gpm, Corrosive/ Caustic Pumping, Eastern, High Temperatures, High/Low pH, HRSG Blowdown, HRSG Pumping, Industrial, Industrial Water, Power Generation, Process Water

Construction of a new combined cycle power plant in Middletown, OH required 3 pump stations for the operation of its HRSG system. Middletown Energy Center uses natural gas and HRSG to generate power, this process requires significant amounts of water for operation.

City of Shafter in California

The City of Shafter|Shafter, CA|400 GPM - 28.5' TDH

jweddell300gpm - 500gpm, Pacific, Replacements & Retrofits, Wastewater

A suburb of the City of Shafter required a lift station package to repair and rehabilitate an existing wastewater sump. Duplex submersible centrifugal pumps and discharge pipe mounting brackets were fitted to a concrete slab poured in the bottom of the existing manhole. The Romtec Utilities package included the proper components to operate in this 26-foot-deep sump. An outdoor MultiSmart control panel utilizes conductive probes for primary and backup level controls and an autodialer for communications. This retrofit package saved about 60% the cost of a new lift station.

Solyndra Commercial Complex

Solyndra|Fremont, CA|450 GPM - 35' TDH

jweddell300gpm - 500gpm, Pacific, Stormwater, Stormwater Runoff

This new commercial complex required two new stormwater pump stations designed to meet low flows of runoff. The manholes and hatches were designed at grade to integrate seamlessly with the brick patio and walkway. Submersible centrifugal pumps in a duplex configuration discharge to below grade valve assemblies accessible by valves cans. The UL listed control panels are contained by stainless steel NEMA enclosures and include intrinsically safe barriers. Both lift stations were designed with the same primary components for site standardization.