Romtec Utilities worked on the replacement of a lift station needed for the 4 separate new facilities which will feed into this lift station.
The City of Laguna Beach|Laguna Beach, CA|600 GPM - 77' TDH
This high flow wet/dry lift station replacement was installed “in the sand” of Main Beach with three dry pit pumps in a 26-feet-deep precast rectangular vault. Triplex split case pumps, sump pumps, an intake/exhaust fan, lights, valves, stairs, and a mezzanine were all provided in the package. The Allen Bradley PLC control panel, flow transmitter, and junction box are located in a control building. Sophisticated SCADA, 3 levels of redundancy, auxiliary power, and an HDPE wet well are all primary components of this package lift station.
City of Colton, CA – Stormwater Runoff Pump Station
74.5GPM
19.7′ TDH
Argent Development Solutions | Beaumont, CA | 467 GPM - 99.3' TDH
The pump station was designed to the City of Beaumont’s standards which have adopted Eastern Municipal Water District requirements, as the city will also be the end owner of the system.
City of Madera, CA | 550 GPM - 25' TDH
The Valley Knolls Development in Carson City, Nevada required a new wastewater station to service the new housing development.