Utica East Ohio Midstream LNG Plant|Kensington, OH|75 GPM - 67' TDH

jweddell50gpm - 100gpm, Eastern, Oil & Gas, Oil/Water Separators, Stormwater, Stormwater Runoff

Utica East Ohio Midstream needed two new pump stations to handle low flows of stormwater runoff at its new Kensington Plant in Ohio. To responsibly contain potentially hazardous stormwater from the topsoil, these pump stations were designed with double-wall fiberglass wet wells with interstitial leak detection. Both pumping systems included corrosion resistant components and sensors due to the potential presences of LNGs in the stormwater runoff. Pumps were engineered with 7.5 hp Ebara pumps in a duplex configuration, and different impellers were specified for each of the two pump stations meet slightly differing head requirements.

condensate pump skid

Condensate Pump Skid|Nederland, Texas| 80' TDH

jweddell5gpm - 50gpm, Corrosive/ Caustic Pumping, Eastern, High Temperatures, High/Low pH, HRSG Blowdown, HRSG Pumping, Industrial, Industrial Water, Power Generation, Process Water

Romtec Utilities designed and supplied a fully engineered condensate pump skid for an industrial hydrogen production facility in Nederland, Texas. This skid-mounted condensate pump system was delivered as a prefabricated, pre-wired pump package tailored to meet the demanding operational, material, and safety requirements of the oil and energy sector.

Kings Mountain Energy Center, HRSG Pump System

Middletown Energy Center|Middletown, OH|480-850 GPM - 25'-35' TDH

jweddell300gpm - 500gpm, 500gpm - 1,000gpm, Corrosive/ Caustic Pumping, Eastern, High Temperatures, High/Low pH, HRSG Blowdown, HRSG Pumping, Industrial, Industrial Water, Power Generation, Process Water

Construction of a new combined cycle power plant in Middletown, OH required 3 pump stations for the operation of its HRSG system. Middletown Energy Center uses natural gas and HRSG to generate power, this process requires significant amounts of water for operation.

Kings Mountain Energy Center, HRSG Pump System

Middletown Energy Center|Middletown, OH|40 GPM - 25' TDH

jweddell5gpm - 50gpm, Corrosive/ Caustic Pumping, Eastern, High Temperatures, High/Low pH, HRSG Blowdown, HRSG Pumping, Industrial, Industrial Water, Power Generation, Process Water

Construction of a new combined cycle power plant in Middletown, OH required 3 pump stations for the operation of its HRSG system. Middletown Energy Center uses natural gas and HRSG to generate power, this process requires significant amounts of water for operation.